Project Timeline

   

-Prior to 2010

Multiple elected officials discuss relocating the County Administration Building due to building 
and site inefficiencies, and poor accessibility.

 

August 2010-

Kenton County Fiscal Court commissions a
 proposal for a planning and programming 
services study
 for the Kenton County
 Administration Building.

 
 

 

-November 2010

The jail moves out of 303 Court Street into the new Kenton County Detention Center.

KCDC

 

2015-

Kenton County Fiscal Court commissions a study to determine costs to renovate the existing County Administration Building.

 

   

-February 2016

Results of study on costs to renovate 303 Court Street presented to Kenton County Fiscal Court.


 

May 2016-

Kenton County Fiscal Court secures purchase option on Bavarian Brewery site. 

 
   

-July 2016

Kenton County Fiscal Court closes on purchase of Bavarian Brewery site.

 

September 2016-

Kenton County Fiscal Court issues a Request for Proposal (RFP) for project management services.

 
   

-October 2016

Kenton County Fiscal Court accepts bid from Parson/Brinckerhoff/WSP to be Project Manager

co branded logo

 

December 14, 2016-

Bavarian Brewery Open House:
Covington Latin School
21 East 11th Street,
Covington, KY 41011
4:00 P.M. to 7:00 P.M.

 
 

 -December 22, 2016

Kenton County Fiscal Court issues a Request for Qualifications (RFQ) for potential Design-Build Teams.

 

January 26, 2017-

Kenton County Continues Work Toward Improving Delivery of Basic Services with Second Open House
Edgewood Senior Center
550 Freedom Park Drive,
Edgewood, KY 41017
4:30 P.M.-6:30 P.M.

 
 

-February 7, 2017

Kenton County Fiscal Court approves three design-build teams to move forward in the RFP process. 

The following teams were selected: 

1. Team led by Turner Construction

David M. Spaulding
Vice President & General Manager
Turner Construction Company
250 West Court Street
Cincinnati, OH 45202
Dspaulding@tcco.com
(513) 721-4224

2. Team led by HGC Construction


Ali Hubbard
Director of Business Development
Mobile: 615-943-1224

Office: 513-861-8866
Fax: 513-861-7878
AHubbard@hgc-group.com

3. Team led by Megen/Turnbull-Wahlert Construction

Tim Sharp
Vice President
Megen Construction Company, Inc.
11130 Ashburn Road
Cincinnati, OH 45240
(513)742-9191
tsharp@megenconstruction.com

Vendors and interested stakeholders are encouraged to contact individual teams directly. 

March 2, 2017-

Release date of RFP for short listed bidders.
 
 

 -June 7, 2017

Proposals are due from short listed bidders. 

June 21, 2017-

After hearing the recommendation from the selection committee, the Fiscal Court unanimously voted to approve the contract with Turner Construction, contingent upon successful contract negotiations.

Learn more about the preferred alternative and alternative concept.

Final Open House for Pre-Design Process for New Kenton County Administration Building
Covington Latin School,
21 East 11th Street,
Covington, KY 41011
4:00 p.m. to 6:00 p.m.

 
 

-June 22- July 7, 2017

Public Comment Period.


July 19, 2017-

Anticipated Completed Contract Execution,
issue NTP.

 


Next Steps-
Preliminary Phases



 

Spring 2017-
Design Phase 

 
 

Fall 2017- Early 2018
Construction Phase 

 
 

Late Spring 2019
Projected move-in date